Search & filter
Search & filter
World Tunnelling Congress
Abstract: In Brasília, Brazil's planned capital, built in the 1950's, a population of 500000 people was predicted, with almost no forethought of underground space use. As Brazil's population grew and the centralization of power in Brasília increased, the population forecast proved wrong, with more than 3 million people currently living in Brazil's capital. Therefore, there are many opportunities for...
Abstract: A tunnel boring machine with an opening in the center of its cutter head, i.e., a donut-shaped tunnel boring machine (DTBM), is proposed. Since the new donut type TBM does not excavate the central section, its assumed excavation characteristics include reduced excavation time, due to reduction of the excavation area and elimination of the use of a center cutter. In order to demonstrate these...
Abstract: In the feasibility study and preliminary design of a metro project, the safety concept represents an essential technical and financial issue that drives some of the main design choices. From the beginning on, a high-level fire safety strategy has to be developed. This allows identifying potentially critical elements, from a constructive and operational point of view, to be considered during...
Abstract: Tseung Kwan O – Lam Tin Tunnel project comprises 2.22 km dual two-lane road tunnels developed to improve connectivity of Central and Eastern Kowloon Area in Hong Kong. For most of the alignment length, the average excavation span of the main tunnels is about 16 m. In one location however, there is a bifurcation where one of the main tunnel drives branches off to the Eastern Harbour Crossing,...
Abstract: Urban development can vastly alter the drainage systems native to a landscape. Along the coastal region of Sydney, the surface expression of deep coastal basins the related upstream tributaries have been altered by a combination of man-made channelisation and stream deviation to accommodate development. As such the original bedrock topography is no longer reflected on the surface....
Abstract: Deep excavations in high permeable ground conditions have always been challenging in underground construction. The case studies herein have deep excavations situated along the major arterial roads and next residential blocks. The Earth Retaining and Stabilizing Structures (ERSS) scheme adopted was diaphragm wall with multiple-levels of steel struts. The geological profile along the longitudinal...
Abstract: Significant cracks on precast reinforced concrete segmental linings of bored tunnel were observed during a regular visual inspection of a rail tunnel. Investigations were carried out to establish the causes of tunnel damage as well as whether the cracks were active. Investigations revealed that the cracks on the segments were due to the consolidation of soft marine clay layer of the Kallang...
Abstract: This paper examines the suitable directional drilling options available for tunnel site investigations. It examines the different drilling methods, borehole survey systems and testing that may be conducted within the hole for lithology, ground fluid and geomechanical parameters. The use of open hole drilling coupled with suitable borehole geophysics is compared with core drilling. The issues of...
Abstract: Early Contractor Involvement (ECI) is a procurement method that involves Contractors in the early phases of project development so that they can influence key design and procurement decisions, particularly assessing the constructability of the design and construction equipment selection. There are many advantages from using this method, but some disadvantages as well. This paper describes the...
Abstract: Tokyo Metro Co. Ltd. operates 9 routes in Capital area of Japan; total length of tunnels is 1.66 km. In Japan, subway tunnels were constructed by the cut & cover method and have typically horizontally oriented double cell box tunnels with rectangular cross sections. Because some tunnels had to be built under narrow roads in Tokyo, there exist some vertically oriented double cell box tunnels...
Abstract: The metro will make its way to the new Istanbul Airport earliest by 2021. There will be two lines, one with a length of 37 km and the other 35 km. There are few lakes left after mining activities carried out along the Metro Line which cause tremendous difficulties during tunnel excavation. This paper summarizes the performance of an EPB TBM and difficulties encountered and precautions taken...
Abstract: New Istanbul Airport is being constructed over an old coal field area of 35 km away from the city center. Sometimes TBM used for tunnel excavation cuts coal seams bearing methane. This paper summarizes the safety problems encountered between chainages of 24+375 km and 24+575 km. A special safety program is used during tunnel excavation. For safety reasons, methane sensors were placed upon TBM...
Abstract: Current practice on tunnel seismic design considers an earthquake ground motion equivalent to a peak ground acceleration and the tunnel lining is designed to sustain the deformation resulting from the application of the earthquake actions. However, what will the behaviour be of the ground motion of a geological fault and its interaction with an intersecting tunnel? This paper concentrates on...
Abstract: New Istanbul Airport is being constructed over an old coal field area of 35 km away from the city center in a very complex geology creating several problems during tunnel construction. This paper summarizes the effect of weathering of a sandstone with different degrees of weathering (W1-W2, W3-4 and W5) on the performance of an EPB-TBM during the construction of Metro Tunnels for Istanbul third...
Abstract: Istanbul New Airport Metro Project is a 38 km long single track metro line, which has in total 76 km of railway length and consists of 69 km TBM tunnels. In order to deal with long TBM tunnel excavations, 10 EPB type TBMs with a diameter of 6,56 meters from 4 different TBM suppliers are used. This paper investigated one of the TBMs which bored through a frequently changing and complex geology...
Abstract: The WestConnex road tunnel project is the largest civil infrastructure project under construction in Australia. The motorway project is being delivered in three stages and is predominantly underground. It includes 33 km of new or improved motorway linking Sydney’s west and southwest with the Central Business District, and the corridor to Sydney Airport and Port Botany. This paper covers Stage...