Lake Mead Intake No. 3 - TBM Tunneling at high pressures

Lake Mead Intake No. 3 - TBM Tunneling at high pressures

itawtcfinal2015croatia

J. Nickerson / R. Bono / C. Cimiotti / E. Moonin

In response to the severe drought on the Colorado River basin and in order to preserve existing water capacity to the Las Vegas Valley, the Southern Nevada Water Authority contracted a new deep-water intake (Intake No. 3) located in Lake Mead. The current project (Contract No. 070F-01-C1) includes three miles of tunnel with very difficult geological conditions and a 650ft deep shaft and marine works. This paper will present the current status of the design-build contract being constructed by Vegas Tunnel Constructors and the challenges and problems faced and the innovative solutions developed to handle the difficult conditions encountered during tunneling with up to 15 bars of pressure.

More details

0,00 €

Year 2015
City Dubrovnik
Country Croatia