Abstract: The breakthrough of the Headrace Tunnel in the Uma Oya project done on the 2nd of October 2019, which face a lot of challenges and unforeseeable geological conditions of 15.4 km. Headrace Tunnel excavated by two hard rock double shield Tunnel Boring Machines (TBMs) with 4.3 m excavation diameter in upward and downward slopes, without any middle access. Upward driven TBM excavated more than 10...