Abstract: With the fast spread of COVID 19 pandemic and the increased logistic difficulties, the Sydhavn Metro extension project in Copenhagen faced a significant risk of delay. To mitigate this delay, an acceleration program was agreed, which included a change of the TBM reception and launching strategy. The response to the pandemic crisis required fast decisions, prompt re-design and close proactive...