Abstract: The construction of the shaft DST-1, 14 m diameter, 65 m deep of the Dugway Storage Tunnel Project (Cleveland), was completed following significant obstacles in the shaft excavation process. After applying different soil treatments (dewatering, jet grouting, permeation grouting) ground freezing was selected as a technically appropriate alternative. Since steel liner plates and ribs were...