Abstract: In an urbanised context, the prediction of movements induced by the excavation of shallow tunnels is a major challenge for both designer (conceptual design) and contractor (detailed design). In the case of mechanised tunnelling with a closed mode tunnel boring machine, the significant number of machine control parameters makes predictive three-dimensional modelling complex. Simplifications are...
Abstract: The Bucharest metro system is actually made of four (4) operating metro lines (Line 1 to Line 4), one line under construction (Line 5), and another one in the design stage (Line 6). The Line 5 (Magistrala 5) is made of twenty-four (24) stations, running from Râul Doamnei station tostation, crossing the city centre in the East-South West direction. The stretch of the Line 5 of the metro system...