Abstract: Within the 10m diameter, 3.5km long Aked tunnel project, part of the Jerusalem-Tel Aviv Rapid Railway, construction of 14 cross passages between the tubes is being executed. Each one implies partially demolishing two rings, on each tube. To transfer the axial forces acting on the opened rings to the adjacent ones and thus provide stability to the lining, reinforced concrete keys installed on...