Abstract: The excavation of the Romanche Gavet underground power station (60 000 m3), which began in May 2012, was completed on August 12, 2015. The project had to face ground model evolution during construction of the main cavern. This paper relates the chronology of events as well as methodologies used during preliminary studies but also during the reengineering phase and the consequences on the...